☀ Solar · Under construction
Sunčana elektrana Radosavci
13,2 MWp
Trošak izgradnje
€11.100.000
40,040 modules (Solvis). CapacityKw = 13.2 MW installed (DC), AcKw = 9.99 MW connection figure, per the source's own two-figure statement. No annual-production estimate is published on the source page, so MonthlyMwh is left NULL rather than invented. Source page's own phrase is "grid connection pending" -- mapped to Status='Under construction' (physically built, not yet delivering to the grid) rather than 'Operational'; CommissionYear left NULL since it has not been commissioned. Note: separate web research for this row found other Croatian coverage describing the plant as already "u probnom radu" (in trial operation), which conflicts with the "grid connection pending" framing -- followed the citing source's own phrase per instruction rather than resolving the discrepancy. Coordinates: settlement-level (Radosavci), not plant-exact. NOTE 2026-07-18: Solvis d.o.o.'s own reference page (https://solvis.hr/reference/?term=elektrane-na-zemlji) cites 11,664.9 kWp for this plant, which matches neither the existing CapacityKw (13200.00, DC) nor AcKw (9990.00, AC) on file -- an unexplained third figure. This plant's Status was 'Under construction'/grid-connection- pending as of the last check, so a possible (unconfirmed) explanation is a different construction phase or a since-revised design capacity, rather than a like-for-like restatement of either figure on file. No values changed here.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
2| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| EPC izvođač | Solvis d.o.o. | Unclaimed | ||
| Vlasnik | HEP | Unclaimed |