8,7 MWp
933 MWh/mo
Pušteno u pogon
2022
Trošak izgradnje
€6.900.000
27,544 modules (Solvis), area ~117,137 m2, built on the site of a former clay factory (ciglana) near the town. CapacityKw = 8.7 MW installed (DC), AcKw = 7.35 MW connection figure, per the source's own two-figure statement. Coordinates: a corner node of OpenStreetMap way 1061783698 ("Sunčana elektrana Obrovac" on openinframap.org), independent of HEP's own site and consistent (within ~1.5 km) with an independently looked-up town-center coordinate for Obrovac. NOTE 2026-07-18: Solvis d.o.o.'s own reference page (https://solvis.hr/reference/?term=elektrane-na-zemlji) cites 7,350 kWp for this plant, which matches the existing AcKw (7350.00, the AC/connection figure) exactly but not CapacityKw (8700.00, the DC/module figure). This is the opposite of Marići (PlantId 37), where Solvis's page clearly cited the DC figure -- so Solvis's own reporting convention is inconsistent across its two solar-page entries for these HEP plants. No values changed here.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
2| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| EPC izvođač | Solvis d.o.o. | Unclaimed | ||
| Vlasnik | HEP | Unclaimed |