2 MWp
183 MWh/mo
Pušteno u pogon
2021
Trošak izgradnje
€2.000.000
Phase 2 expansion on the same Sabadin site as Kaštelir 1. 9,240 modules from domestic manufacturer Solvis, area ~40,000 m2. CapacityKw uses the AC figure; the source publishes no separate DC/nameplate figure for this plant. Coordinates: same site as Kaštelir 1 (see that row for sourcing); also cross-checked against OpenStreetMap way 1088108669 (openinframap.org entry "Sunčana elektrana Kaštelir 2"), which maps this specific plant as its own polygon.
Izvor podataka: https://www.hep.hr/projekti/obnovljivi-izvori-energije/neintegrirane-sunceve-elektrane/3422
Strane i prijave uloga
2| Uloga | Tvrtka | Status | Preuzeo/la | Radnje |
|---|---|---|---|---|
| EPC izvođač | Solvis d.o.o. | Unclaimed | ||
| Vlasnik | HEP | Unclaimed |